Pavement Solutions will continue microsurfacing the city of Warsaw today.
Posted
-
Pavement Solutions will continue microsurfacing the city of Warsaw today.
Today will begin Day 18 of the project.
Today: Washington Street, Alpha Street, Gable Drive, Pieta Street, St Marys Drive.
Day 19, Tuesday: Prairie Street, Westcreek Drive, Latta Street
Day 20, Wednesday: Herscher Drive, Ra Mar Street, Woodlawn Drive, Crestlane Drive
Day 21, Thursday: Buffalo Street, Edgewater Drive, Deer Trail
Day 22, Friday: Gilliam Drive, Gilliam Drive South and North
Day 23, Saturday: Sheridan Street
Day 24, Sunday: Little Eagle Drive, Channelview Drive, Baythorne Drive
Day 25, Aug. 28: Fairlane Drive, Miner Drive
Day 26, Aug. 29: Osborn Street, Miner Drive, Lakewood Hills Drive