Microsurfacing Roadwork Continues Around Warsaw

Posted
Pavement Solutions will continue microsurfacing the city of Warsaw streets through mid-September.

The project should be completed Sept. 13, weather pending.

This list will include the final nine days of the project and will be updated in the case of a weather delay. Today begins Day 29 for the project.

• Monday, Day 29: Gable Drive, Pieta Street, St. Marys Drive, Edgewood Drive, Alpha Street, Leedy Street

• Wednesday, Day 30: Herscher Drive, Woodlawn Drive, Ra Mar Street, Deer Trail

• Thursday, Day 31: Baker Street, Academy Court, Tyner Street, Buffalo Street

• Friday, Day 32: Eisenhower Parkway, Little Eagle Drive

• Saturday, Day 33: Sheridan Street

• Sunday, Day 34: Edgewater Drive, Crestlane Drive, Miner Drive

• Sept. 11, Day 35: Fairlane Drive, Baythorne Drive, Channelview Drive, Gilliam Drive

• Sept. 12, Day 36: Gilliam Drive, Gilliam Drive North, Gilliam Drive South

• Sept. 13, Day 37: Osborn Street, Miner Drive, Lakewood Hills Drive, Main Street (Union to Columbia), Lake Street (Jefferson to Winona).