AKRON – Architecture firm Fanning Howey gave the Tippecanoe Valley School Board an update on the school corporation’s 2022 building project Thursday.

Michael K. Schipp, principal project leader at Fanning Howey, said Fanning Howey scheduled a meeting with Tippecanoe Valley High School Principal Brandon Kresca and scheduled staff meetings with all the departments that are impacted by the project. He said the company also has monthly leadership meetings with Superintendent Blaine Conley and his team, so everyone’s informed. Fanning Howey has had meetings with the high school teams twice and have more meetings next week. The company has 11 meetings to date with 34 staff members with the high school.

“Now that we’ve got the scope kind of established, now we want to take it into a little bit more detail to other people, even custodial, technology, coaches and some of those things,” Schipp said. Everyone has been very responsive in regards to their needs in the project and it has been a very good process, he said.

Schipp went over some of the changes to the plans for the project.

Some of the changes included added a small training room and coaches’ office by the locker room.

From the field house, Fanning Howey has heard from the community meetings about people wanting to see the courts from a spectator point of view. Changes were made to the middle of the field house to accommodate spectators seeing what’s going on.

For the agriculture classrooms, the design allows for the classroom to be as flexible as possible. One of the changes is the ceiling design allows for students to hang experiments. There is a passthrough door between the two agriculture classes because Schipp said students may need to share equipment between the two classrooms.

For the auditorium, the design tries to maximum seating. One of the changes to the design was to take a out what Schipp referred to as a “bumatory” in the middle of the auditorium in order to add 30 more seats for a total of approximately 649 seats, Schipp said.

Another change would be to make the pool deeper. Schipp said the current pool is 3 feet 6 inches. Scott V. Cherry, senior vice president of Fanning Howey, said the current minimum depth for a pool is 4 feet. Schipp said it was for diving purposes.

Schipp said he is planning on having his pool consultant take a look at the pool.

He said the project schedule includes updates to the Board in November. On Dec. 20, Fanning Howey will update the Board on the project and request authorization to send work out to the bid and release the bid documents to bidders on Dec. 21.

In January, there will be a pre-bid conference with potential bidders with the receipt of bills to be done by Feb. 1. Fanning Howey is looking to award the contracts on Feb. 1 and commence the construction March 1.

In other business, TVHS moved to virtual learning last week due to the number of quarantines, Conley said.

According to a previous press release from TVSC, TVHS and Burket Education Center reverted to virtual instruction (remote learning) starting Sept. 7 and returned to in-person instruction on Sept. 13.

TVSC will remain mask optional for students and staff and the corporation will continue to monitor cases as its done in the past, he said. The corporation continues to report its cases to the Indiana State Department of Health and the corporation appreciates “our Valley family and community support and understanding.”

During Monday’s school board meeting, elementary and middle school principals will present the iLearn results to the Board from 2021. There will be data for the Board to look at.

The Board will also have its budget hearing and be asked to accept several donations at Monday’s meeting.

The Mentone Alumni is donating $250 to the student activities funds at Mentone Elementary School, Conley said.

The biggest donation the Board will be asked to approve is a $100,000 Indiana Department of Homeland Security grant.

This year, the focus will be replacing and updating a lot of the security cameras in the school corporation, as well as the corporation’s subscription to its Raptor system, Conley said.

AKRON – Architecture firm Fanning Howey gave the Tippecanoe Valley School Board an update on the school corporation’s 2022 building project Thursday.

Michael K. Schipp, principal project leader at Fanning Howey, said Fanning Howey scheduled a meeting with Tippecanoe Valley High School Principal Brandon Kresca and scheduled staff meetings with all the departments that are impacted by the project. He said the company also has monthly leadership meetings with Superintendent Blaine Conley and his team, so everyone’s informed. Fanning Howey has had meetings with the high school teams twice and have more meetings next week. The company has 11 meetings to date with 34 staff members with the high school.

“Now that we’ve got the scope kind of established, now we want to take it into a little bit more detail to other people, even custodial, technology, coaches and some of those things,” Schipp said. Everyone has been very responsive in regards to their needs in the project and it has been a very good process, he said.

Schipp went over some of the changes to the plans for the project.

Some of the changes included added a small training room and coaches’ office by the locker room.

From the field house, Fanning Howey has heard from the community meetings about people wanting to see the courts from a spectator point of view. Changes were made to the middle of the field house to accommodate spectators seeing what’s going on.

For the agriculture classrooms, the design allows for the classroom to be as flexible as possible. One of the changes is the ceiling design allows for students to hang experiments. There is a passthrough door between the two agriculture classes because Schipp said students may need to share equipment between the two classrooms.

For the auditorium, the design tries to maximum seating. One of the changes to the design was to take a out what Schipp referred to as a “bumatory” in the middle of the auditorium in order to add 30 more seats for a total of approximately 649 seats, Schipp said.

Another change would be to make the pool deeper. Schipp said the current pool is 3 feet 6 inches. Scott V. Cherry, senior vice president of Fanning Howey, said the current minimum depth for a pool is 4 feet. Schipp said it was for diving purposes.

Schipp said he is planning on having his pool consultant take a look at the pool.

He said the project schedule includes updates to the Board in November. On Dec. 20, Fanning Howey will update the Board on the project and request authorization to send work out to the bid and release the bid documents to bidders on Dec. 21.

In January, there will be a pre-bid conference with potential bidders with the receipt of bills to be done by Feb. 1. Fanning Howey is looking to award the contracts on Feb. 1 and commence the construction March 1.

In other business, TVHS moved to virtual learning last week due to the number of quarantines, Conley said.

According to a previous press release from TVSC, TVHS and Burket Education Center reverted to virtual instruction (remote learning) starting Sept. 7 and returned to in-person instruction on Sept. 13.

TVSC will remain mask optional for students and staff and the corporation will continue to monitor cases as its done in the past, he said. The corporation continues to report its cases to the Indiana State Department of Health and the corporation appreciates “our Valley family and community support and understanding.”

During Monday’s school board meeting, elementary and middle school principals will present the iLearn results to the Board from 2021. There will be data for the Board to look at.

The Board will also have its budget hearing and be asked to accept several donations at Monday’s meeting.

The Mentone Alumni is donating $250 to the student activities funds at Mentone Elementary School, Conley said.

The biggest donation the Board will be asked to approve is a $100,000 Indiana Department of Homeland Security grant.

This year, the focus will be replacing and updating a lot of the security cameras in the school corporation, as well as the corporation’s subscription to its Raptor system, Conley said.

Have a news tip? Email [email protected] or Call/Text 360-922-3092

e-Edition


e-edition

Sign up


for our email newsletters

Weekly Top Stories

Sign up to get our top stories delivered to your inbox every Sunday

Daily Updates & Breaking News Alerts

Sign up to get our daily updates and breaking news alerts delivered to your inbox daily

Latest Stories


Caucus Chooses Zaugg For Winona Lake Town Council Seat
WINONA LAKE — Jason Zaugg is the newest member of the Winona Lake Town Council.

Warsaw School Board Approves Superintendent’s Contract
Warsaw School Board approved the retirement of one Warsaw Community Schools administrator and the contract of another Monday.

Warsaw Council OKs Second Readings Of Salary Ordinances
Five of the seven items before the Warsaw Common Council on Monday were second readings, including four salary ordinances and one additional appropriation ordinance.

4 Injured In Two-Vehicle Accident Friday
Four people were injured during an accident on North CR 400E, 300 feet north of East CR 100N, in Warsaw Friday.

Feed My Starving Children Event Kicks Off
Feed My Starving Children on Monday kicked off its seventh packing event to help children around the world.