TVHS Stage Should Be Poured Soon
May 17, 2024 at 9:19 p.m.

AKRON — Workers should pour the new Tippecanoe Valley High School auditorium stage next week.
At its monthly public work session on Thursday, the Tippecanoe Valley School Board heard that information from The Skillman Corp. Project Manager Scott Rogers. The Skillman Corp. is the construction management company for TVHS’ ongoing construction project, of which the auditorium is part.
Other plans for the next month in the auditorium are to finish bricking the stage wall and begin work on light fixtures and reflector ceilings.
For the new agriculture area, the construction crew worked on walls over the last month, which they will drywall and paint over the next month.
As for the pool, it was tested for leaks in the last month, with workers to install tile in the pool tank over the next month.
All work is estimated to be done around September.
AKRON — Workers should pour the new Tippecanoe Valley High School auditorium stage next week.
At its monthly public work session on Thursday, the Tippecanoe Valley School Board heard that information from The Skillman Corp. Project Manager Scott Rogers. The Skillman Corp. is the construction management company for TVHS’ ongoing construction project, of which the auditorium is part.
Other plans for the next month in the auditorium are to finish bricking the stage wall and begin work on light fixtures and reflector ceilings.
For the new agriculture area, the construction crew worked on walls over the last month, which they will drywall and paint over the next month.
As for the pool, it was tested for leaks in the last month, with workers to install tile in the pool tank over the next month.
All work is estimated to be done around September.