Winona Roundabout Bid At Nearly $3M

April 20, 2022 at 1:59 a.m.
Winona Roundabout Bid At Nearly $3M
Winona Roundabout Bid At Nearly $3M

By Leah Sander-

WINONA LAKE — A bid has been accepted for work on Winona Lake's future roundabout.

Winona Lake Town Manager Craig Allebach let the Winona Lake Town Council know that news at its meeting Tuesday.

The Indiana Department of Transportation, which is working with the town on the roundabout set to be constructed at Park Avenue, Kings Highway, Argonne Road and Winona Avenue, rebid the project recently. The winning bidder was Phend & Brown for $2,989,989.

The project had to be rebid because when the initial bidding period occurred in January, there was only one bidder and the bid came in too high. However, as Allebach explained Tuesday, this bidding period didn't run smoothly either.

"The rebid, we were hoping to try and keep it the same, maybe a little bit lower. It came very close to not being bid again, but was bid," Allebach said.

For the project, INDOT is footing 80% of the bill, with the town providing 20%.

Allebach said one of the next steps in the process is having a pre-construction meeting, but he isn't sure of a timeline for that happening yet.

While the actual construction of the roundabout hasn't started yet, work has been going on the site for a while with those driving in the area being unable to go under the overpass on Argonne.

NIPSCO is currently doing utility work for the project, said Allebach.

"They will be there, last I heard, until the second week in May," he said. "So they're putting all new electric in — with the understanding that the electric was supposed to be done actually, but I see they're out there today working on electric, so maybe they are behind. ... And then they were going to finish up the gas the second week in May.

"They're putting a big 8-inch main, I believe, through there ... putting in new electric, new gas," he said.

Prior to NIPSCO's utility work there, Warsaw completed a storm drain project, Allebach said.

WINONA LAKE — A bid has been accepted for work on Winona Lake's future roundabout.

Winona Lake Town Manager Craig Allebach let the Winona Lake Town Council know that news at its meeting Tuesday.

The Indiana Department of Transportation, which is working with the town on the roundabout set to be constructed at Park Avenue, Kings Highway, Argonne Road and Winona Avenue, rebid the project recently. The winning bidder was Phend & Brown for $2,989,989.

The project had to be rebid because when the initial bidding period occurred in January, there was only one bidder and the bid came in too high. However, as Allebach explained Tuesday, this bidding period didn't run smoothly either.

"The rebid, we were hoping to try and keep it the same, maybe a little bit lower. It came very close to not being bid again, but was bid," Allebach said.

For the project, INDOT is footing 80% of the bill, with the town providing 20%.

Allebach said one of the next steps in the process is having a pre-construction meeting, but he isn't sure of a timeline for that happening yet.

While the actual construction of the roundabout hasn't started yet, work has been going on the site for a while with those driving in the area being unable to go under the overpass on Argonne.

NIPSCO is currently doing utility work for the project, said Allebach.

"They will be there, last I heard, until the second week in May," he said. "So they're putting all new electric in — with the understanding that the electric was supposed to be done actually, but I see they're out there today working on electric, so maybe they are behind. ... And then they were going to finish up the gas the second week in May.

"They're putting a big 8-inch main, I believe, through there ... putting in new electric, new gas," he said.

Prior to NIPSCO's utility work there, Warsaw completed a storm drain project, Allebach said.
Have a news tip? Email [email protected] or Call/Text 360-922-3092

e-Edition


e-edition

Sign up


for our email newsletters

Weekly Top Stories

Sign up to get our top stories delivered to your inbox every Sunday

Daily Updates & Breaking News Alerts

Sign up to get our daily updates and breaking news alerts delivered to your inbox daily

Latest Stories


Via Credit Union Wins State Level Awards
Via Credit Union Wins State Level Awards

Benefits Of Compound Interest Highlight Importance Of Investing Early
Investing when you’re young can have the potential to produce impactful earnings gains. And that’s because of a simple concept: compounding.

Court News 10.19.24
The following people have filed for marriage licenses with Kosciusko County Clerk Ann Torpy:

Public Occurrences 10.19.24
County Jail Bookings The following people were arrested and booked into the Kosciusko County Jail:

Warsaw Wraps Up Regular Season With Blowout Over Northridge
Playing the final game of the regular season Friday night, the Warsaw football team looked to end the campaign on a high not with a trip to Middlebury to take on Northridge. Thanks to some outstanding defense as well as two special teams scores, the Tigers were able to head into sectional play with a three-game winning streak under their belts with a 42-13 win.