Warsaw Schools’ Activity Center To Be Completed By July 2019

April 24, 2018 at 5:23 p.m.
Warsaw Schools’ Activity Center To Be Completed By July 2019
Warsaw Schools’ Activity Center To Be Completed By July 2019


The Warsaw Community High School Student Activity Center (SAC) is slated to be completed by July 30, 2019, the school board learned Monday night.

Chief Financial Officer Dr. Brandon Penrod told the board bids for the SAC were opened April 12. The bids were for subcontracts for earth work, electrical work, etc.

“Wiegand (Construction) verified those bids as responsive and responsible,” Penrod said before introducing Dave Jankowski, Wiegand Construction vice president, preconstruction, to explain the contract.

WCS’ contract for the SAC construction is with Wiegand Construction, which holds the contracts with all the subcontractors.

The SAC will include flexible education space, a track, a tournament area and a clinic, according to previous information. It will be built next to the WCHS pool area.

The contract with Wiegand, which was initially approved months ago, was reapproved by the school board Monday now that all the financial numbers available.

Jankowski told the board they are looking at a “substantial completion date” of July 30 of 2019.

After the meeting, WCS Superintendent Dr. David Hoffert said the final cost of the SAC and improvements to the high school is under $10 million.

A few alternatives, like polished concrete and extra painting, were able to be added.

The $10 million cost is the cap to make the project tax neutral, according to a previous Times-Union article.

During Monday’s meeting, the board also held a public hearing on the proposed renovation and improvements to school facilities, including HVAC, roofing and site improvements and the purchase of equipment, vehicles and technology and construction of a health center. No members of the public asked questions or made any comments during the hearing.

Penrod said that pursuant to Indiana Code, a school corporation financing more than $1 million to build or repair a school building must hold a public hearing in which the explanations of the potential value of the project to the school corporation and to the community are given.

“These projects fit into Warsaw Community Schools’ long-range facility plan, and this bond for this project does not affect the tax rate, does not increase the tax rate,” Penrod said.

After the hearing was concluded, the school board unanimously approved the project resolution and the preliminary bond resolution.



The Warsaw Community High School Student Activity Center (SAC) is slated to be completed by July 30, 2019, the school board learned Monday night.

Chief Financial Officer Dr. Brandon Penrod told the board bids for the SAC were opened April 12. The bids were for subcontracts for earth work, electrical work, etc.

“Wiegand (Construction) verified those bids as responsive and responsible,” Penrod said before introducing Dave Jankowski, Wiegand Construction vice president, preconstruction, to explain the contract.

WCS’ contract for the SAC construction is with Wiegand Construction, which holds the contracts with all the subcontractors.

The SAC will include flexible education space, a track, a tournament area and a clinic, according to previous information. It will be built next to the WCHS pool area.

The contract with Wiegand, which was initially approved months ago, was reapproved by the school board Monday now that all the financial numbers available.

Jankowski told the board they are looking at a “substantial completion date” of July 30 of 2019.

After the meeting, WCS Superintendent Dr. David Hoffert said the final cost of the SAC and improvements to the high school is under $10 million.

A few alternatives, like polished concrete and extra painting, were able to be added.

The $10 million cost is the cap to make the project tax neutral, according to a previous Times-Union article.

During Monday’s meeting, the board also held a public hearing on the proposed renovation and improvements to school facilities, including HVAC, roofing and site improvements and the purchase of equipment, vehicles and technology and construction of a health center. No members of the public asked questions or made any comments during the hearing.

Penrod said that pursuant to Indiana Code, a school corporation financing more than $1 million to build or repair a school building must hold a public hearing in which the explanations of the potential value of the project to the school corporation and to the community are given.

“These projects fit into Warsaw Community Schools’ long-range facility plan, and this bond for this project does not affect the tax rate, does not increase the tax rate,” Penrod said.

After the hearing was concluded, the school board unanimously approved the project resolution and the preliminary bond resolution.



Have a news tip? Email [email protected] or Call/Text 360-922-3092

e-Edition


e-edition

Sign up


for our email newsletters

Weekly Top Stories

Sign up to get our top stories delivered to your inbox every Sunday

Daily Updates & Breaking News Alerts

Sign up to get our daily updates and breaking news alerts delivered to your inbox daily

Latest Stories


Trump Can’t Be Trusted
Editor, Times-Union: If you are a Republican who cares about this country and the direction it is headed, these are a few examples of many respected Republicans, including former staffers and supporters expressing no confidence in Trump. You can vote for Harris on a split ticket and still vote for your other preferred Republican candidates.

Time To Step Up
Editor, Times-Union: If you need the truth about what’s going on in the country, read Newsmax Magazine. They tell it like it is.

Apology To Lassus
Editor, Times-Union: My name is Nicholas Richcreek, and I’d like to apologize to Lassus Handy Dandy for the event that happened last year.

Public Occurrences 10.28.24
County Jail Bookings The following people were arrested and booked into the Kosciusko County Jail:

Jane F. Kantner
MENTONE – Jane F. Kantner, 89, of Mentone, passed at 7:44 a.m. Saturday, Oct. 26, 2024, at her home.