Change Order For Main St. Project Tops $70K

September 3, 2016 at 4:14 a.m.


After the Warsaw Board of Public Works and Safety approved a $70,000 change order and pay application Friday morning for the Main Street sewer replacement project, the board members heard that the project encountered a problem.
The change order request was for Wessler Engineering, Fort Wayne.
Brian Davison, wastewater treatment utility manager, said about $33,000 of the $70,410 total change order “was for the next reach of pipe (120 feet long) beyond the project we were supposed to. That next reach of pipe was discovered to be in really poor condition, so we went ahead and replaced it while we were there.”
The rest of the change order was because they ran into poor soils, extra laterals, thicker pavement than expected and other corrections, he said.
Mayor Joe Thallemer asked, “So the big part though was that extra stretch of pipe that was found to be defective?” Davison said that was correct.
“How are things going on Main Street?” Thallemer asked a few minutes later.
“Good, until today,” Davison replied.
“So we’ll talk,” Thallemer said. “I know you guys have been working hard down there.” Thallemer agreed to talk to Davison about the problem after the Board of Works meeting.
Thallemer said he understood that sometimes workers don’t know what they’re dealing with until they get down into the project and see the pipes and their conditions. He said the Main Street neighbors have been very patient.
During the meeting, Davison said asphalt is scheduled for Wednesday.
After the meeting, Davison elaborated more on the problem that was discovered Friday.
“I don’t think it’s going to be too much of a problem. We have a manhole at the west end of the project with the whole bottom out. We’ve got to figure out how to fix it. A company is coming out Tuesday to look at it,” Davison said.
He said they want to try and maintain the project’s paving schedule, but the Main Street paving may be pushed back to Thursday.
In other business, the board approved:
• For Warsaw Parks & Recreation Department Recreation Director Sheila Wieringa to apply for a grant with the Kosciusko County Community Foundation for $5,000. The money would be used to continue support of the Central Park Concert Series.
• For Wieringa to apply for a grant with Kosciusko REMC Operation Round Up for $1,500. The grant would be used to continue support of the annual Family Carnival, which will be Aug. 4 in 2017.
• A contract between the Parks Department and Susan Grossman for $100. Grossman will offer a Yoga Basics workshop from 5:15 to 6 p.m. on four Wednesdays from Oct. 5 to 26 at the Pete Thorn Center gymnasium. Wieringa said she thinks the workshops will have better attendance than before since they’re being moved from lunch time to the evening.
• A Husky Trail project pay application for $1,470 to A&Z Engineering LLC for right-of-way acquisition services. The city will be reimbursed for 80 percent of the cost from the Indiana Department of Transportation. City Planner Jeremy Skinner said he believed this was the last pay application for engineering services for rights of way on Husky Trail.
Skinner said they’re hoping for bid letting to happen in December or January, with construction beginning in spring of  2017.
• An East Market Street project pay application for $9,587.52 for preliminary engineering services to VS Engineering Inc. The city will be reimbursed for 80 percent of the costs by INDOT.
Skinner said they’re just at the beginning stages of this project, but it’s moving along and a construction start date could be in spring 2018. He is scheduling a meeting with INDOT for within the next month.
• A Buffalo Street redevelopment project pay application for $6,834.48 for design engineering services by American Structurepoint Inc. The completion of the design for the project is very near, Skinner indicated.
At the end of the meeting, Skinner introduced his new assistant planner, Justin Taylor. Taylor is a Ball State University graduate who has been doing free lance work in Chicago.

After the Warsaw Board of Public Works and Safety approved a $70,000 change order and pay application Friday morning for the Main Street sewer replacement project, the board members heard that the project encountered a problem.
The change order request was for Wessler Engineering, Fort Wayne.
Brian Davison, wastewater treatment utility manager, said about $33,000 of the $70,410 total change order “was for the next reach of pipe (120 feet long) beyond the project we were supposed to. That next reach of pipe was discovered to be in really poor condition, so we went ahead and replaced it while we were there.”
The rest of the change order was because they ran into poor soils, extra laterals, thicker pavement than expected and other corrections, he said.
Mayor Joe Thallemer asked, “So the big part though was that extra stretch of pipe that was found to be defective?” Davison said that was correct.
“How are things going on Main Street?” Thallemer asked a few minutes later.
“Good, until today,” Davison replied.
“So we’ll talk,” Thallemer said. “I know you guys have been working hard down there.” Thallemer agreed to talk to Davison about the problem after the Board of Works meeting.
Thallemer said he understood that sometimes workers don’t know what they’re dealing with until they get down into the project and see the pipes and their conditions. He said the Main Street neighbors have been very patient.
During the meeting, Davison said asphalt is scheduled for Wednesday.
After the meeting, Davison elaborated more on the problem that was discovered Friday.
“I don’t think it’s going to be too much of a problem. We have a manhole at the west end of the project with the whole bottom out. We’ve got to figure out how to fix it. A company is coming out Tuesday to look at it,” Davison said.
He said they want to try and maintain the project’s paving schedule, but the Main Street paving may be pushed back to Thursday.
In other business, the board approved:
• For Warsaw Parks & Recreation Department Recreation Director Sheila Wieringa to apply for a grant with the Kosciusko County Community Foundation for $5,000. The money would be used to continue support of the Central Park Concert Series.
• For Wieringa to apply for a grant with Kosciusko REMC Operation Round Up for $1,500. The grant would be used to continue support of the annual Family Carnival, which will be Aug. 4 in 2017.
• A contract between the Parks Department and Susan Grossman for $100. Grossman will offer a Yoga Basics workshop from 5:15 to 6 p.m. on four Wednesdays from Oct. 5 to 26 at the Pete Thorn Center gymnasium. Wieringa said she thinks the workshops will have better attendance than before since they’re being moved from lunch time to the evening.
• A Husky Trail project pay application for $1,470 to A&Z Engineering LLC for right-of-way acquisition services. The city will be reimbursed for 80 percent of the cost from the Indiana Department of Transportation. City Planner Jeremy Skinner said he believed this was the last pay application for engineering services for rights of way on Husky Trail.
Skinner said they’re hoping for bid letting to happen in December or January, with construction beginning in spring of  2017.
• An East Market Street project pay application for $9,587.52 for preliminary engineering services to VS Engineering Inc. The city will be reimbursed for 80 percent of the costs by INDOT.
Skinner said they’re just at the beginning stages of this project, but it’s moving along and a construction start date could be in spring 2018. He is scheduling a meeting with INDOT for within the next month.
• A Buffalo Street redevelopment project pay application for $6,834.48 for design engineering services by American Structurepoint Inc. The completion of the design for the project is very near, Skinner indicated.
At the end of the meeting, Skinner introduced his new assistant planner, Justin Taylor. Taylor is a Ball State University graduate who has been doing free lance work in Chicago.
Have a news tip? Email [email protected] or Call/Text 360-922-3092

e-Edition


e-edition

Sign up


for our email newsletters

Weekly Top Stories

Sign up to get our top stories delivered to your inbox every Sunday

Daily Updates & Breaking News Alerts

Sign up to get our daily updates and breaking news alerts delivered to your inbox daily

Latest Stories


Public Occurrences 05.14.25
County Jail Bookings The following people were arrested and booked into the Kosciusko County Jail:

Fat & Skinny Tire Festival’s 20th Year Feels Surreal To Co-Founder
WINONA LAKE - For Fat & Skinny Tire Fest co-founder and co-director Greg Demopoulos, the fact that this weekend is the 20th year for the three-day bicycling event is surreal.

Nappanee Man Injured In Turkey Hunting Accident In Fulton County
A Nappanee man was injured in a turkey hunting accident Saturday in Fulton County.

Breakfast Optimist Club Car Show Is Sunday
Warsaw Breakfast Optimist Club is hosting the 15th Annual City of Lakes Car Show on Sunday, May 18 from noon to 5 p.m. in downtown Warsaw at the courthouse square.

Huntington Teen Arrested On Rape, Child Molesting Charges
A Huntington teen was arrested after allegedly forcing a minor under 14 to have sex.