Syracuse Wrestles With Costs Of Water Project

July 28, 2016 at 4:25 p.m.

By KRISTA ZARTMAN, Times-Union Correspondent-

SYRACUSE - "Where do we go from here," was the question, and "I'm not certain," the frequent answer, at Tuesday's special Syracuse Town Council meeting.

The board met with representatives from Greeley and Hansen to discuss the town's water distribution project and expected to get a final dollar amount for the project, along with a final draft of building plans. Instead they got a newer, higher-than-expected estimate and a "95 percent complete" plan.

Initially, the plan was estimated to cost $4.2 million. Last night, the estimate climbed closer to $7.2 million and though the board assembled specifically to review final documents, they were handed the 95-percent version instead.

"What's the hold up?" town manager Jeff Noffsinger asked after Stan Diamond, of Greeley and Hanson, announced the plans were not complete. "We were on track this summer to have plans submitted to IDEM by October and now it's November."

Diamond was not certain.

He was certain, however, as to why the project cost has dramatically risen. Time delays resulted in higher material and construction costs.

"Factors outside our control have significantly impacted the cost," Diamond said. "Primarily the construction and development in China has caused a rise in the price of steel."

Bill Musser, board member, questioned the engineering firm, asking how they, as professionals and experts in their field, could underestimate by nearly 50 percent.

"I don't care about what's going on in China," Musser said. "How can you be so far off?"

The representatives from the firm were not certain.

The town did learn Tuesday they have "other options." They can eliminate any and all "frills" from the project, or borrow more money, Diamond told them.

Eliminating the extras could save a few hundred thousand and steps already were taken to eliminate a "five-page list" of extra things, from flagpoles to asphalt to a third well and pump.

Even with these things the final cost estimate is high. Originally, the town borrowed $7 million from the State Revolving Loan Fund, anticipating the need to spend, at the very most, $6 million. The extra money was a safety net of sorts. Now, paring the project down to the minimum exceeds the funds available.

Paul Stoelting asked a simple question: "How are we going to pay for that?" Until final plans are submitted, it seems that will continue to be asked and meanwhile, construction continues to be delayed, and "prices continue to rise." [[In-content Ad]]

SYRACUSE - "Where do we go from here," was the question, and "I'm not certain," the frequent answer, at Tuesday's special Syracuse Town Council meeting.

The board met with representatives from Greeley and Hansen to discuss the town's water distribution project and expected to get a final dollar amount for the project, along with a final draft of building plans. Instead they got a newer, higher-than-expected estimate and a "95 percent complete" plan.

Initially, the plan was estimated to cost $4.2 million. Last night, the estimate climbed closer to $7.2 million and though the board assembled specifically to review final documents, they were handed the 95-percent version instead.

"What's the hold up?" town manager Jeff Noffsinger asked after Stan Diamond, of Greeley and Hanson, announced the plans were not complete. "We were on track this summer to have plans submitted to IDEM by October and now it's November."

Diamond was not certain.

He was certain, however, as to why the project cost has dramatically risen. Time delays resulted in higher material and construction costs.

"Factors outside our control have significantly impacted the cost," Diamond said. "Primarily the construction and development in China has caused a rise in the price of steel."

Bill Musser, board member, questioned the engineering firm, asking how they, as professionals and experts in their field, could underestimate by nearly 50 percent.

"I don't care about what's going on in China," Musser said. "How can you be so far off?"

The representatives from the firm were not certain.

The town did learn Tuesday they have "other options." They can eliminate any and all "frills" from the project, or borrow more money, Diamond told them.

Eliminating the extras could save a few hundred thousand and steps already were taken to eliminate a "five-page list" of extra things, from flagpoles to asphalt to a third well and pump.

Even with these things the final cost estimate is high. Originally, the town borrowed $7 million from the State Revolving Loan Fund, anticipating the need to spend, at the very most, $6 million. The extra money was a safety net of sorts. Now, paring the project down to the minimum exceeds the funds available.

Paul Stoelting asked a simple question: "How are we going to pay for that?" Until final plans are submitted, it seems that will continue to be asked and meanwhile, construction continues to be delayed, and "prices continue to rise." [[In-content Ad]]

Have a news tip? Email [email protected] or Call/Text 360-922-3092

e-Edition


e-edition

Sign up


for our email newsletters

Weekly Top Stories

Sign up to get our top stories delivered to your inbox every Sunday

Daily Updates & Breaking News Alerts

Sign up to get our daily updates and breaking news alerts delivered to your inbox daily

Latest Stories


AWL To Hold ‘Empty The Shelters’ Event Starting Thursday
PIERCETON – Starting Thursday and going through May 15, the Animal Welfare League of Kosciusko County is reducing the adoption fees for adult dogs and cats and kittens sponsored through the Bissell Pet Foundation’s spring Empty the Shelters event.

County Health Board Discusses Birth Certificates, Funding For Health First Kosciusko
Kosciusko County Board of Health members held a regular meeting Monday to discuss changes regarding birth and death certificates in Indiana and funding needs in Kosciusko County.

Milford Man Arrested For Criminal Recklessness While Armed With A Deadly Weapon
A Milford man was arrested after allegedly firing a shotgun in the air two times.

Syracuse Man Arrested After Allegedly Impersonating Law Enforcement Officer
A Syracuse man was arrested after allegedly impersonating a law enforcement officer.

North Webster YMCA Celebrates Renovations, New Equipment
NORTH WEBSTER - For over 20 years, the YMCA has had a presence in the North Webster Community Center (NWCC).