Milling, Paving Planned Next Week
July 28, 2016 at 4:25 p.m.
By -
During this time, parking will be prohibited in these areas and motorists are advised to avoid them.
On Tuesday milling will begin on Indiana Street between Market and Main streets; Lake Street between Winona Avenue and Center street; and West Street between Porter and Lake streets, depending on the progress of the first two streets.
On Wednesday milling will begin on West Street between Port and Lake streets, depending on Tuesday’s progress; Lincoln Street between Market and Center streets; Normandy Drive; Wayside Court; (Old) Patterson Road west of Normandy Drive.
On Thursday and Oct. 25, the milled locations will be paved. Paving should be complete by the end of the day Oct. 25, weather permitting.[[In-content Ad]]
During this time, parking will be prohibited in these areas and motorists are advised to avoid them.
On Tuesday milling will begin on Indiana Street between Market and Main streets; Lake Street between Winona Avenue and Center street; and West Street between Porter and Lake streets, depending on the progress of the first two streets.
On Wednesday milling will begin on West Street between Port and Lake streets, depending on Tuesday’s progress; Lincoln Street between Market and Center streets; Normandy Drive; Wayside Court; (Old) Patterson Road west of Normandy Drive.
On Thursday and Oct. 25, the milled locations will be paved. Paving should be complete by the end of the day Oct. 25, weather permitting.[[In-content Ad]]
Have a news tip? Email [email protected] or Call/Text 360-922-3092